Completed Project

A curated selection of EPC projects delivered across Oil & Gas, Renewables, and Industrial sectors. Each card links to a detailed case study with scope, KPIs, and deliverables.

🔧 EPC   🔗 Commissioning   🖥️ SCADA/DCS   📈 Performance KPIs

Filters
At a Glance
On-time Delivery
95%
Oil & Gas
2025
WM32 Well Manifold – Mechanical Completion & 100-Well Connection – Pre-Commissioning, Commissioning and Strat-up
Bapco Upstream, Awali Oil Fields, Kingdom of Bahrain

Mechanical Completion (MEI) and punch-list closure for the WM32 Well Manifold with 100 wells connected, including full design documentation updates and redline mark-ups. Scope included system-wise PSSR execution and Redline Marked up (RLM) verification for: earthing system, high-power distribution, lighting and small-power networks, UPS and LVSG panels, control and automation systems, instrument air package, fuel gas system, header modules, separator packages, produced liquid system and associated pipeline tie-ins, RCS12 Pipeline #1, AG pipeline tie-in, chemical injection system, closed drain package, flare system, F&G system, safety shower & eye wash package, and fencing & access road infrastructure.

Redline Marked up (RLMs) and Verifications
MEI / Mechanical Completion
PSSR (System-Wise)
Loop Testing
Control Narrative Checks (CN PL)
Cause & Effects Checks (C&E PL)
Punch-List Closure: MEI PL
IFAT PL SCADA
SAT PL IAC
Loop Check PL
CN PL
C&E PL
Control System PL
N₂ Purging
Overall Plant PSSR
100 Wells Connected
Plant Startup

End User:
Bapco Upstream, Awali Oil Fields, Kingdom of Bahrain

Oil & Gas
2025
ADNOC LNG TRAIN 1&2 REJUVENATION PROJECT-EPC DAS ISLAND (2023- 2025)
Das Island – Abu Dhabi – UAE

Verification, Validation, Engineering, Procurement, Construction & Commissioning

  1. Underground Cement Lined Piping (WP-1)
  2. Major and Medium Criticality Machinery – Pumps (WP-2)
    • Replacing the Lube Oil Cooler of MP, HP Carbonate pumps and Lean DEA pumps
    • Replacing mechanical governor for MP, HP and Lead DEA pumps
  3. Instrumentation (WP-7)
    • Replacing existing CCC compressor controllers (Series 3) with CCC prodigy rack and card based system
    • Replacement of ESD Valves (62 Nos)
    • Replace Plant-43 fire water pump local control panels (02)
    • Replace MRB critical components
    • Replace CW Hydraulic discharge valve 68” (06)
    • Replace the obsolete Plant-42 band/bar screen control system with new system
    • Replace Control Valves CV pneumatic positioners with smart positioners
  4. Control System (WP-8 + TSR) Modification, Migration and Upgradation of DCS System (Honeywell), ESD, F&G System (Triconex)
  5. Electrical (WP-9) Modification, Replacement, and Retrofitting of Switchgear at Substations
  6. Total Sulphur Reduction (TSR)
  7. FAT, SAT, ISAT of the Packages
  8. All Electrical field related works
  9. Field Instruments, F&G Detectors, Control/Shutdown Valves, PSVs/TRVs and Analyzers of TSR scope
  10. Preparation of Constructability Review Workshop for: WP7, WP8, and WP79
Key Activities
  • Project
  • Engineering
  • Procurement

End User:ADNOC – Abu Dhabi – UAE

Oil & Gas
2025
EU3 HYDROGEN EXTRATION UNIT FOR BOROUGE 3 PROJECT EPC (2024-Jan- 2025)
ABU DHABI POLYMERS COMPANY LTD. (BOROUGE) / ADNOC
  1. PSA2 FG Compressors (1st, 2nd stage)
  2. PSA2 OG Compressors
  3. PSA2 unit Vessels
  4. C4 Guard Adsorber Cooler Dripleg
  5. C4 Guard Regen Gas Cooler
  6. Coalescer
  7. TA related material
  8. Process measurement monitoring
  9. FAT, SIT, SAT of the Packages
  10. Switchgear
  11. DCS/ESD System, F&G System
  12. All Electrical related works
  13. Field Instruments, F&G Detectors, Control/Shutdown Valves, PSVs/TRVs and Analyzers
Key Activities
  • Project Engineering
  • Procurement

End User: ADNOC

In Progress Project

A curated selection of EPC projects delivered across Oil & Gas, Renewables, and Industrial sectors. Each card links to a detailed case study with scope, KPIs, and deliverables.

🔧 EPC   🔗 Commissioning   🖥️ SCADA/DCS   📈 Performance KPIs

Filters
At a Glance
On-time Delivery
95%
Oil & Gas
2025
WM33 Well Manifold – Mechanical Completion & 100-Well Connection – Pre-Commissioning, Commissioning and Strat-up
Bapco Upstream, Awali Oil Fields, Kingdom of Bahrain

Mechanical Completion (MEI) and punch-list closure for the WM33 Well Manifold with 100 wells connected, including full design documentation updates and redline mark-ups. Scope included system-wise PSSR execution and Redline Marked up (RLM) verification for: earthing system, high-power distribution, lighting and small-power networks, UPS and LVSG panels, control and automation systems, instrument air package, fuel gas system, header modules, separator packages, produced liquid system and associated pipeline tie-ins, RCS12 Pipeline #1, AG pipeline tie-in, chemical injection system, closed drain package, flare system, F&G system, safety shower & eye wash package, and fencing & access road infrastructure.

Redline Marked up (RLMs) and Verifications
MEI / Mechanical Completion
PSSR (System-Wise)
Loop Testing
Control Narrative Checks (CN PL)
Cause & Effects Checks (C&E PL)
Punch-List Closure: MEI PL
IFAT PL SCADA
SAT PL IAC
Loop Check PL
CN PL
C&E PL
Control System PL
N₂ Purging
Overall Plant PSSR
100 Wells Connected
Plant Startup

End User:
Bapco Upstream – Kingdom of Bahrain 

Oil & Gas
2025
WM33 Well Manifold – Mechanical Completion & 100-Well Connection – Pre-Commissioning, Commissioning and Strat-up
Abu Safah Field, Bapco Upstream, Kingdom of Bahrain

Mechanical Completion (MEI) and punch-list closure for the WM32 Well Manifold with 100 wells connected, including full design documentation updates and redline mark-ups. Scope included system-wise PSSR execution and Redline Marked up (RLM) verification for: earthing system, high-power distribution, lighting and small-power networks, UPS and LVSG panels, control and automation systems, instrument air package, fuel gas system, header modules, separator packages, produced liquid system and associated pipeline tie-ins, RCS12 Pipeline #1, AG pipeline tie-in, chemical injection system, closed drain package, flare system, F&G system, safety shower & eye wash package, and fencing & access road infrastructure.

Redline Marked up (RLMs) and Verifications
MEI / Mechanical Completion
PSSR (System-Wise)
Loop Testing
Control Narrative Checks (CN PL)
Cause & Effects Checks (C&E PL)
Punch-List Closure: MEI PL
IFAT PL SCADA
SAT PL IAC
Loop Check PL
CN PL
C&E PL
Control System PL
N₂ Purging
Overall Plant PSSR
100 Wells Connected
Plant Startup

End User:
Bapco Upstream – Kingdom of Bahrain